Rajasthan RE Storage Incentive: 100% Transmission & Wheeling Waiver — Eligibility Criteria
Rajasthan RE Storage Incentive: 100% Transmission & Wheeling Waiver is open to startups registered in India. The full eligibility criteria — qualifying sectors, states and entity types — are below.
Who can apply
Who this is for: developers of Renewable Energy (RE) integrated Storage projects in Rajasthan. Eligibility rests on how the project is built, not on the profile of the promoter.
- The project must combine renewable generation with battery storage. Standalone renewable plants, or storage built without renewable generation alongside it, do not match the project type described for this incentive.
- The Battery Energy Storage System (BESS) capacity must be more than 30% of the project's total RE capacity. Projects whose storage share falls at or under that mark do not qualify.
- Compliance with the storage-to-generation ratio has to be demonstrated through project documentation when the claim is filed.
The policy summary does not set out separate turnover, age or funding-stage conditions for this incentive, and eligibility is assessed at the point of application. There is no application window to miss — the incentive is open throughout the year.
Rajasthan RE Storage Incentive: 100% Transmission & Wheeling Waiver is open to startups at any stage working in energy climate and mobility transport. The programme is targeted at startups registered in Rajasthan. Applicants should be registered as private limited, llp and opc.
- Eligible stage
- Any stage
- Location
- Open to startups registered in India
- Entity type
- Private Limited, Llp, Opc, Partnership, Proprietorship
← Back to Rajasthan RE Storage Incentive: 100% Transmission & Wheeling Waiver overview